Bridges & Structural Infrastructure
Sportsmans Creek New Bridge
Client
Roads and Maritime Services (now Transport for NSW)
Duration
May 2016 – February 2018
Location
Lawrence NSW
Expertise
Bridge Design, Construction and Maintenance, Demolition, Road Construction
The ageing structure was replaced with a new bridge 100 metres upstream, resolving ongoing safety risks and significant maintenance expenses.
Project Scope
- Earthworks, including clearing and grubbing, removal and stockpiling of topsoil, excavation of cuttings, placing of general fill and offsite disposal of spoil material
- Construction of a 175-metre-long two-lane structure incorporating a 2.5m off-road shared path for cyclists and pedestrians
- Realignment and upgrade of approximately 200m of the southern approach and 520m of the northern approach, including intersections and adjoining road integration
- Protecting and relocating public utility services
- Permanent and temporary erosion and sediment controls
- Surface and subsurface drainage works
- Modification of access to the existing boat ramp/Flo Clark Park
- Landscaping and revegetation
Key Challenges
Replacing an Ageing Structure That No Longer Met Community Needs
The existing bridge had become costly to maintain, and did not meet the long‑term access, safety, or capacity needs of the Lawrence community. We delivered a new 175‑metre two‑lane structure positioned 100 metres upstream, eliminating the safety risks and ongoing maintenance burden of the former timber bridge and ensuring reliable access for the region well into the future.
Realigning and Upgrading Key Road Approaches
Replacing the bridge required the realignment of surrounding roads to be integrated with the new structure. Our team completed major roadworks, including the upgrade of approximately 200 metres of the southern approach and 520 metres of the northern approach. This involved earthworks, drainage, erosion controls, service relocations, and intersection improvements.
Maintaining Access for Pedestrians, Cyclists, and Marine Users During Construction
As a vital corridor for residents, recreational users, and waterway traffic, construction needed to avoid disruption. We developed and implemented stringent traffic, pedestrian, and marine management plans to maintain access throughout the project. The new design includes a 2.5‑metre off‑road shared path, and works also incorporated modifications to the boat ramp and nearby park areas. This ensured the community remained safely connected during project delivery and beyond.